671 results found

  1. Repro steps:
    1. Create a 20 day task
    2. Create 5 consecutive days of holidays in the middle of that task.
    3. Turn on 'show holidays' - observe task is 20 days. Good, assuming people are working through the holidays.
    4. Turn off 'show holidays' - observe task is 15 days. Bad, assuming people are not working through the holidays.

    Expected: the task is 20 days regardless of whether or not holidays are shown.

    As an aside, it would be nice to separate the display of holidays and whether or not people work on holidays.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  2. Ability to rename Fields in Heath Report "OK", "Behind", "Overdue" as this report is used for stakeholder updates. A task that spans several days, and effort is only 2 hrs a day is not Overdue if day one progress is not updated. "Caution" would be a better reflection from a PM point of view.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  3. Health Report to display without needing a license: 15/07/2020 - TeamGantt Chat

    Ability to display a saved view of the Health Report in our internal intranet website so that our Senior Leadership Team and other key stakeholders can View it. It will save time (LEAN) as remove the need to save and upload snapshhots, It will be a real time view, it will not need a licence/per user for having ability to see the report (create more buy in to value of this product / IT team ability to deliver projects).

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  4. I would love if cards were organized in groups in teamgantt where the group name in teamgantt corresponded to the list name in trello. Card = task. List = group! Everytime I create a new card in a list I have to move it to the correct group in teamgantt.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  5. Needs continuous scrolling while dragging an item vertically / higher in a list or dragging a Milestone horizontally outside the visible screen boundary. (Example: Trello automatically adjusts the screen when moving lists, etc outside the visible screen instead of dropping the item to manually scroll up on the screen, then having to go back and find where the item was dropped, which many times is creating a "New Group Task" or "New Task" which then requires deletion)

    PS: Was told within Chat box to use arrow keys which doesn't work. Was told to use a trackpad which I really don't…

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  6. Multiple Project Display Order: Just happened upon this answer in an advanced video. This is a basic, but valuable feature.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  7. 1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  8. Outdent seems to only be available to 'first level' sub-groups. (I guess a person could outdent this first level, then proceed to outdent sub-groups, but outdent on a right click flyout menu would be quickest)

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  9. Fix your "export to PDF" to match the displayed chart. Let me know when you've fixed it and I'll trial the software again. BTW it was going so well compared with our other trials until I tried to print the chart.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  10. 1) Difference between "Insert Task Below" and "Insert Sub-Group"
    2) How to move items within a Sub-Group while maintaining it's indent
    3) How to un-indent / un-sub-group

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  11. When planning routine marketing campaign, multiple operations of the same nature (i.e. mailing) are related to the same TASK (mailing to customers via....). It would be handy to enter all of them into one task line (say, once a week)

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  12. I know it sounds simple. IT's all I want. I want to say:
    "Redesign of X" will take 5 days and either start on 11/3 or will depend on this other task. That's it. This is the most basic functionality anyone would want. After 10 minutes of fiddling, I could enter a task name but not a duration or dependency... unless that's all done via the dragging of the bars. If so, I'll pass.
    No reply needed. Just feedback to you may retain the next guy who comes along.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  13. When using your time tracker, it is difficult to get to the "Stop Timer" button at the bottom of the popup window. The time tracking window is large to fully display when the software is maximized for the desktop window and there is no scroll bar to scroll down and access the lower part of the window. I am using MS Edge with TeamGantt displaying on full screen. I have to go to the timesheet in order to access the stop timer button.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  14. When using your time tracker, it is difficult to get to the "Stop Timer" button at the bottom of the popup window. The time tracking window is large to fully display when the software is maximized for the desktop window and there is no scroll bar to scroll down and access the lower part of the window. I am using MS Edge with TeamGantt displaying on full screen. I have to go to the timesheet in order to access the stop timer button.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  15. Similar to how Gmail allows the user to select how dense / compact the UI layout is, it would be good to have that option in TeamGantt because the top inch of my screen feels wasted (spacious layout of the top-level navigation and the submenus below it). I'd be happy to sacrifice that screen real estate to give me a larger view of the Gantt chart.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  16. Print checklists for use on-site. These could be used in determining at the end of the day, what progress was made.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  17. I would like to be able to generate a summary of our time spent across our various projects in 2020. Is this possible, in terms of a report?

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  18. have a resources available from date to avoid scheduling someone who is not available

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  19. FYI - Your password reset feature doesn't appear to work. I've reset the password following through the whole process twice (email, click link, new password accepted) - keeps the previous password.

    1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  20. 1 vote
    Vote

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
    You have left! (?) (thinking…)
    0 comments  ·  Admin →
    How important is this to you?

    We're glad you're here

    Please sign in to leave feedback

    Signed in as (Sign out)
  • Don't see your idea?