Add a weighting for percentage completion
Team Gantt bases percentage completion only on time. Good for some not all projects. If we are laying 3 km of water pipe over 2 months and are monitoring water quality over 6 months the water quality will have 3 times the weight even though it costs a hundredth of the pipeline and requires little resource. We need a simple optional weighting system so that we can weight tasks to give a more realistic picture of progress.