upgrade your tool to be compatible with e.g. Open Project/ Miscrosoft Project
We intend to use your tool, however what I do miss for project management is the functionality:
1. critical path generation
2. Finish Finish relations
3. time related dependencies, (e.g. a task can start after an other task has progressed 40%)
Can you please indicate whether and when you plan to incorporate these functions, as I believe they are essential for detail project management activities. (on high level in e.g. acquisition phase it is already an interesting tool, in particular the possibility to use it on the web) best regards