Ability to set a baseline per task
It would be great to be able to set a baseline per task rather than on all tasks at once. That way if you need to add new tasks or shift existing tasks then you won't have to create a baseline at the project level for all tasks at once.
example usage:
I've set a baseline on my project for all of my tasks. However due to a new production I need to add a number of new tasks to my schedule, additionally some of my original tasks have exceeded their baselines. If I want to add baselines to the new tasks I will have to create a new baseline for all of my tasks effectively "resetting" the existing baselines on anything that that has exceeded it's original schedule.
I believe an option to set it per project, per group or per task would be ideal