I totally agree with Suzanne and Ryan. SS, FF, SF, FS with buffer either in absolute values (e. g. days) or percentage. For example a task can not start before the other one has 50% progressed. Or two days before one task is finished the other one must start.
Also multiple constraints are important because more than one task can depend on one other.